Hi All,
Lots going on with the build.
We had some delays with HVAC installation and Electrician but now finally on track. I ended up decoupling the floor with Hush Frame silicone decouplers and then added another two layers of tongue and groove 3/4" sub floor. Feels super solid yet with a hint of bounce.

All the walls are also decoupled from the main structure with hush frame decouplers and have been double dry walled with green glue. All the walls are super stiff and have a super solid feel. Mudding begins tomorrow.

My electrician went a bit mad and put in 9 x 20 amp circuits and 2 x 30 amp circuits for the sub amp which will be a 6.4Kw amp pushing 3200w to each 18" JTR RS1 Sub.